- The Pump and Columns were pulled, disassembled and inspected, clearances checked and repaired as required.
- Columns were fabricated, anodes installed, hydro-tested and then coated.
- Pump shaft and bowls bushings were replaced.
- A UL listed, FM approved engine was sourced and a Randolph right angled gearbox was sized accordingly.
- A drive shaft was sized.
- The skid was designed, fabricated and tested.
- Diesel fuel tank was fabricated and tested.
- A PLC controlled panel was designed and assembled.
- Engine was wired and tested.
- Pump, gearbox and engine was installed and aligned.
- Unit was tested and commissioned.